Front Wheelhouse Front Panel Replacement - Brazing

Note : According to different corrosion warranties, only the regional mandatory joining methods are allowed.

Removal Procedure

    Warning : Refer to Approved Equipment for Collision Repair Warning in the Preface section.

    Warning : Refer to Glass and Sheet Metal Handling Warning in the Preface section.

  1. Disable the SIR system. Refer to SIR Disabling and Enabling .
  2. Disconnect the battery negative cable. Refer to Battery Negative Cable Disconnection and Connection : without Start/Stop System .
  3. Remove all related panels and components.
  4. Visually inspect the damage. Repair as much of the damage as possible.
  5. Remove the sealers and anti-corrosion materials from the repair area as necessary. Refer to Anti-Corrosion Treatment and Repair : Base .

  6. 2505525
  7. Locate and mark all the necessary factory welds of the front wheelhouse front panel (1).
  8. Drill all factory welds. Note the number and location of welds for installation of the service assembly.

  9. 2372889
  10. Drill hidden factory weld (1) where front wheelhouse front panel and front wheelhouse overlap.

  11. 2505526
  12. Remove the front wheelhouse front panel (1).

Installation Procedure


    2505527
  1. Create 6x20 mm (4/16 x 12/16 in) slots for brazing along the edges of the front wheelhouse front panel (1) as noted from the original panel.

  2. 2372892
  3. Create 6x20 mm (4/16 x 12/16 in) slots for brazing (1) where front wheelhouse front panel and front wheelhouse overlap.
  4. Clean and prepare the attaching surfaces for brazing.

  5. 2505526
  6. Position the front wheelhouse front panel (1) on the vehicle.
  7. Verify the fit of the front wheelhouse front panel.
  8. Clamp the front wheelhouse front panel into position.

  9. 2505528
  10. Braze the front wheelhouse front panel (1) accordingly.

  11. 2372894
  12. Braze the joint from front wheelhouse front panel (1) to front wheelhouse accordingly.
  13. Apply the sealers and anti-corrosion materials to the repair area as necessary. Refer to Anti-Corrosion Treatment and Repair : Base .
  14. Paint the repaired area.
  15. Install all related panels and components.
  16. Connect the battery negative cable. Refer to Battery Negative Cable Disconnection and Connection : without Start/Stop System .
  17. Enable the SIR system. Refer to SIR Disabling and Enabling .
   