Quarter Outer Panel Sectioning

Special Tools

    • BO-6392 Flanging Tool Kit
    • BO-6396 Bonding Pliers

For equivalent regional tools, refer to Special Tools .

Removal Procedure

    Warning: Refer to Approved Equipment for Collision Repair Warning in the Preface section.

    Warning: Refer to Collision Sectioning Warning in the Preface section.

    Warning: Refer to Glass and Sheet Metal Handling Warning in the Preface section.

  1. Disable the SIR system. Refer to SIR Disabling and Enabling .
  2. Disconnect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  3. Remove all related panels and components.
  4. Visually inspect the damage. Repair as much of the damage as possible.
  5. Remove the sealers and anti-corrosion materials from the repair area, as necessary. Refer to Anti-Corrosion Treatment and Repair .

  6. 2327332
  7. Create cut lines on the quarter outer panel.

  8. 2327331

    Note: Do not damage any inner panels or reinforcements.

  9. Cut the panel where sectioning is to be performed.

  10. 2327330
  11. Open the wheelhouse flanging.

  12. 2327329
  13. Locate and mark all the necessary factory welds of the quarter outer panel.
  14. Drill all factory welds. Note the number and location of welds for installation of the service assembly.

  15. 2327328
  16. Remove the damaged quarter outer panel.

Installation Procedure


    2327327
  1. Cut the quarter outer panel in corresponding locations to fit the remaining original panel. The sectioning joint should be trimmed to allow a gap of one-and-one-half-times the metal thickness at the sectioning joint.
  2. Create a 50 mm (2 in) backing plate from the unused portion of the service part.
  3. Drill a 8 mm (5/16 in) along the sectioning cut on the remaining original part. Locate these holes 13 mm (1/2 in) from the edge of part and spaced 40 mm (1 1/2 in) apart.
  4. Prepare all mating surfaces as necessary.
  5. Fit the backing plates halfway into the sectioning joints, clamp in place and plug weld to the vehicle.
  6. Align the quarter outer panel.

  7. 2327326
  8. Drill 8 mm (5/16 in) for plug welding along the edges of the quarter outer panel as noted from the original panel.
  9. Clean and prepare the attaching surfaces for welding.

  10. 2327325
  11. Apply one-part windscreen urethane adhesive (1) as noted from the original panel.
  12. Position the quarter outer panel on the vehicle.
  13. Verify the fit of the quarter outer panel.
  14. Clamp the quarter outer panel into position.

  15. 2327324
  16. Plug the weld accordingly.
  17. To create a solid weld with minimum heat distortion, make 25 mm (1 in) stitch welds along the seam with 25 mm (1 in) gaps between them. Then go back and complete the stitch weld.
  18. Pre-flange the flange with BO-6396 pliers and BO-6392 tool kit.

  19. 2327323
  20. Finish closing the wheelhouse flanging.
  21. Apply the sealers and anti-corrosion materials to the repair area, as necessary. Refer to Anti-Corrosion Treatment and Repair .
  22. Paint the repaired area. Refer to Basecoat/Clearcoat Paint Systems .
  23. Install all related panels and components.
  24. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  25. Enable the SIR system. Refer to SIR Disabling and Enabling .
   


© Copyright Chevrolet. All rights reserved