To the top of the document
Cruze
   
GMDE Start Page Load static TOC Load dynamic TOC Help?

Front Wheel housing Panel Replacement - MIG-Brazing

Note : According to different corrosion warranties, only the regional mandatory joining methods are allowed.

Removal Procedure

    Warning : Refer to Approved Equipment for Collision Repair Warning in the Preface section.

    Warning : Refer to Glass and Sheet Metal Handling Warning in the Preface section.

  1. Disable the SIR System. Refer to SIR Disabling and Enabling .
  2. Disconnect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  3. Remove all related panels and components.
  4. Visually inspect the damage. Repair as much of the damage as possible.
  5. Remove the sealers and anti-corrosion materials from the repair area, as necessary. Refer to Anti-Corrosion Treatment and Repair : Base .

  6. 2027988

    Note : Front wheelhouse rear panel brace (1) remains to the body.

  7. Locate and mark all the necessary factory welds of the front wheelhouse.

  8. 2027990
  9. Drill all factory welds. Note the number and location of welds for installation of the service assembly.

  10. 2027991
  11. Cut the adhesive in the front area (1) and where the front wheelhouse and the front compartment side rail overlap (2) with an appropriate tool.

  12. 2027992
  13. Remove the front wheelhouse.

Installation Procedure


    2027993
  1. Remove the front wheelhouse rear panel brace (1) from service panel.

  2. 2027995
  3. Create 6 x 20 mm (4/16 x 12/16 in) slots for MIG-brazing along the edges of the front wheelhouse (1).
  4. Clean and prepare the attaching surfaces for brazing.

  5. 2027991

    Note : In MIG-brazing areas 50 mm (2 in) must be kept clear of structural adhesive.

  6. Apply structural adhesive on the front area (1) and create 6 x 20 mm (4/16 x 12/16 in) slots for MIG-brazing where the front wheelhouse and the front compartment side rail overlap (2).

  7. 2027992
  8. Position the front wheelhouse on the vehicle.
  9. Verify the fit of the front wheelhouse.
  10. Clamp the front wheelhouse into position.

  11. 2027996
  12. Braze accordingly.
  13. Apply the sealers and anti-corrosion materials to the repair area, as necessary. Refer to Anti-Corrosion Treatment and Repair : Base .
  14. Paint the repaired area. Refer to Basecoat/Clearcoat Paint Systems .
  15. Install all related panels and components.
  16. Connect the negative battery cable. Refer to Battery Negative Cable Disconnection and Connection .
  17. Enable the SIR system. Refer to SIR Disabling and Enabling .
   


© Copyright Chevrolet. All rights reserved